Projects

South Baghdad gas power plant 2 Flame scanner Baker Hughes for gas turbine GE FR5 Supplied (2024)

AL-Taji Power plant Gas turbine sonsumable GE FR6 (2024)

Al-Taji Power Plant Flame Scanner for gas turbine FR5 & FR6 Supplied (2024)

South Baghdad gas power plant 1 PRESS OIL Filter 200 L/m used to remove metal particles from quenching oil, transformer oil, insulation oil, gear oil, hydraulic oil, turbine oil, light fuel oil and compressor oil etc, it also can remove less water. Economic, easy operation and maintenance. Supplied (2024).

South Baghdad gas power plant 1 Mobile Vacuum Turbine Oil Purifier -Model (1800 Liters/Hour) Designed for Turbine Oil Purification, developed with vacuum evaporation technology, coacervation technology, coalescing technology, separating engineering technology and refined purification
technology. It can eliminate water, gas, impurities, colloid, dielectric etc. rapidly and effectively in high vacuum situation and make the waste oil reuse. Supplied (2024)

Najibiyah Power Plant Bray solenoid valves (2024)

AL-Taji Power plant IGV for GE FR5 (2024)

Al-Najaf New Power Plant 2019

We have supplied the new power plant that was being established in Al-Najaf with the following materials:-

  • Rotor Earth Fault Transmitter (BRUSH)
  • Rotor Earth Fault Aerial (BRUSH)

This project was done and delivered within less than the required time limit (22 weeks) while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

Al-Najaf New Power Plant 2019 (2)

We have supplied the new power plant that was being established in Al-Najaf with the following materials:-

  • Rotor Earth Fault Receiver (BRUSH)

his project was done and delivered within less than the required time limit (150 days) while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

General Electricity Company for the southern regions (Bazerkan Gas Plant) (2018)

We have supplied the power plant that was being established in Bazerkan with the following materials:-

  • S318495701 Bearing Brush (BRUSH)
  • S318495801 Bearing Brush (BRUSH)
  • S320277801 Bearing Oil Seal Kit (BRUSH)
  • S320136201 Bearing Oil Seal Kit (BRUSH)

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

General Company of Electrical Energy Production in the Southern Regions (Basrah) (2022)

We have supplied the power plant that was being established in Al Basrah with the following branching power plants :-

Power Plants :-

  • Khor Al Zubair
  • Rumaila

The following materials were provided for each of the power plants correspondingly :-

  • 40 ZOK 27 210 Litre Drums – Khor Al Zubair
  • 60 ZOK 27 210 Litre Drums – Al Rumaila

This project was done and delivered within less than the required time limit (21 Days) while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

Al Quds Power Plant – General Company of Electrical Energy Production in the Middle Region (2019 – 2022)

We have supplied the power plant that was being established in Al Quds power plant with the following materials from the periods of 2019 to 2022 :-

  • 60 ZOK 27 210 Litre Drums – 2019
  • 20 ZOK 27 210 Litre Drums – 2020
  • 40 ZOK 27 210 Litre Drums – 2021
  • 40 ZOK 27 210 Litre Drums – 2022

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

Al Musayib Power Plant – General Company of Electrical Energy Production in the Middle Euphrates Region (2017 – 2018)

We have supplied the power plant that was being established in Al Musayib power plant with the following materials from the periods of 2017 to 2018 :-

  • 10 ZOK 27 210 Litre Drums – 2017
  • 10 ZOK 27 210 Litre Drums – 2018

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

Mada’in Al Iraq (Private Company) – Al Basrah (2018)

We have supplied the private company of Mada’in Al Iraq that is located in Al Basrah with the following materials in 2018 :-

  • 20 ZOK 27 210 Litre Drums – 2018

Taha and Partners CO. (Private Company) – Baghdad (2019)

We have supplied the private company of Taha and Partners that is located in Baghdad with the following materials in 2019 :-

  • 10 ZOK 27 1000 Litre Drums Demin Water – 2019

General Electricity Company for the Southern Regions (Bazerkan Plant) (2017) – The Former General Directorate for Electricity Production in Basrah

We have supplied the power plant that was being established in Bazerkan with the following materials:-

  • 13 ZOK 27 210 Litre Drums

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

General Electricity Company for the Southern Regions (Bazerkan Plant) (2019)

We have supplied the power plant that was being established in Bazerkan with the following materials:-

  • 60 Mobil Jet Oil 254 Barrels
  • 20 Mobil Jet Oil II Barrels
  • 20 Mobile Hydraulic Oil, ISO VG 32 Barrels

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

General Directorate of Electrical Energy Transfer in the Middle Euphrates Region (Al Hilah) (2014)

We have supplied the power plant that was being established in Al Hilah with the following materials:-

  • 4 Alstom 400 KV High Voltage Bushing

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

General Directorate of Electrical Energy Production in the Middle Euphrates Region (Al Najaf Gas Power Plant) (2013)

We have supplied the power plant that was being established in Al Najaf with the following materials:-

  • RMG 512 Gas Pressure Regulator

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

General Directorate of Electrical Energy Production in the Middle Euphrates Region (Al Hindiya – Al Kufah Hydroelectric Power Plant) (2014)

We have supplied the hydroelectric power plant that was being established in Al Hindiya – Al Kufah with the following materials:-

  • 2 Electric Signal Transmitter

This project was done and delivered within less than the required time limit (2015) while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

General Directorate of Electrical Energy Production in the Middle Euphrates Region (Al Hilah Gas Power Plant ) (2014)

We have supplied the gas power plant that was being established in Al Hilah with the following materials:-

  • 2 Newton Derby PM Generator Type F7375

This project was done and delivered within less than the required time limit (2014) while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

General Directorate of Electrical Energy Production in the Middle Euphrates Region – Al Khayrat Power Plant (2020)

We have supplied the electrical power plant that was being established in Al Khayrat Power Plant with the following materials:-

  • Mark 6E Controller

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

General Directorate of Electrical Energy Production in the Middle Region – Al Quds Power Plant (2019 -2020)

We have supplied the electrical power plant that was being established in Al Quds Power Plant with the following materials:-

  • Exciter System Brush Electrical Machines Brushless Exciter

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

General Directorate of Electrical Energy Production in the Middle Euphrates Region – Al Hillah Power Plant

We have supplied the electrical power plant that was being established in Al Hillah with the following materials:-

  • 3 Alstom Lightning Arrester Systems
  • 3 Alstom Current Transformers
  • 3 Alstom Voltage Transformers

This project was done and delivered within less than the required time limit (24 Months) while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

General Directorate of Electrical Energy Production in the South Region – Bazerkan Gas Plant (2019)

We have supplied the gas electrical power plant that was being established in Bazerkan with the following materials:-

  • Pratt & Whitney Hydraulic Actuator – Variable Stator with LVDT

This project was done and delivered within less than the required time limit (60 days) while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

General Directorate of Electrical Energy Production in the South Region – Bazerkan Gas Plant (2019)

We have supplied the gas electrical power plant that was being established in Bazerkan with the following materials:-

  • 8 Electro Switch Breaker Control Switch with two positions
  • 10 Electro Switch Control Switch with three positions

This project was done and delivered within less than the required time limit (60 days) while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

General Directorate of Electrical Energy Production in the South Region – Bazerkan Gas Plant (2019)

We have supplied the gas electrical power plant that was being established in Bazerkan with the following materials:-

  • 3 Atkomatic 30800 Series Stainless Steel, Semi-direct Lift High Pressure Valve

This project was done and delivered within less than the required time limit (90 days) while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

General Company of Electrical Energy Production in the Middle Euphrates Region (2015 – 2016) – Al Najaf Electrical Gas Power Plant – Formerly known as General Directorate of Electrical Energy Production in the Middle Euphrates

We have supplied the gas electrical power plant that was being established in Al Najaf Gas Power Plant with the following materials:-

  • Alfa Laval Oil Cleaning Module (OCM)

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

Ministry of Oil – Al Wasat Refinery Company (2016)

We have supplied the refinery company that was being established in Al Wasat Oil Refineries with the following materials:-

  • 20 Ton Turkish Cast Iron for building materials

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

Al Quds Power Plant – General Company of Electrical Energy Production in the Middle Region (2023)

We have supplied the refinery company that was being established in Al Quds with the following materials:-

  • 2x Oil Cleaning Module Machine

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

Ministry of Electricity – Multiple Stations in Various Regions of Iraq (2023)

We have supplied the Ministry of Electricity of Iraq in Various Power Stations in various regions with the following materials:-

  • Sodium Hypochlorite
  • Sodium Hydroxide

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

Ministry of Electricity – Multiple Stations in Various Regions of Iraq (2023)

We have supplied the Ministry of Electricity of Iraq in Various Power Stations in various regions with the following materials:-

  • 56 Daulco, Inc. Check Valve 120 Pascal Per Square Inch Max Operating Pressure

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

Ministry of Electricity – Multiple Stations in Various Regions of Iraq (2023)

We have supplied the Ministry of Electricity of Iraq in Various Power Stations in various regions with the following materials:-

  • 12 X-Flow XF55 Membrane hydrophilic hollow-fiber ultrafiltration filters

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

Ministry of Electricity – Multiple Stations in Various Regions of Iraq – (2023)

We have supplied the Ministry of Electricity of Iraq in Various Power Stations in various regions with the following materials:-

  • 100 Veolia CleanBlade GTC1000 Barrel

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

Ministry of Electricity – Multiple Stations in Various Regions of Iraq – (2023)

We have supplied the Ministry of Electricity of Iraq in Various Power Stations in various regions with the following materials:-

  • 1 15kV Powell®️ PowlVac®️ Circuit Breaker

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

Al Quds Power Plant – General Company of Electrical Energy Production in the Middle Region (2023)

We have supplied the Al Quds Power Plant – General Company of Electrical Energy Production in the Middle Regions with the following materials:-

  • 1 USA EVOQUA® Continuous Electrodeionization (CEDI) – EDI Water Filter

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

South Baghdad Power Station 2 – General Company of Electrical Energy Production in the Middle Region (2023)

We have supplied the South Baghdad Power Station 2 – General Company of Electrical Energy Production in the Middle Region with the following materials:-

  • 1 USA EVOQUA® Continuous Electrodeionization (CEDI) – EDI Water Filter

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

Al Hayba Office – Directorate of Water Resources in Anbar – General Authority for the Operation and Maintenance – Hit District (2004)

We have supplied the Directorate of Water Resources in Anbar with the following materials:-

  • 10 Cubic Meters – Reverse Osmosis Water Filteration System – Jordanian Production

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

Private Parties – (2005)

We have supplied private parties with the following materials:-

  • 2x 1 Cubic Meters – Reverse Osmosis Water Filteration System – Jordanian Production

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equiping the power plant site with the affromentioned materials.

Al-Sadder Power Plant (2024)

We have supplied private parties with the following materials

  • 5x 1 Power Supply

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equipping the power plant site with the aforementioned materials.

Al Quds Power Plant – General Company of Electrical Energy Production in the Middle Region (2024)

We have supplied the Al Quds Power Plant – General Company of Electrical Energy Production in the Middle Regions with the following materials:-

  • 21x 1 FR9 SL+MOUNTING BRACKET

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equipping the power plant site with the aforementioned materials.

Al-Najaf Power Plant

We have supplied the Al Al-Najaf Station with the following materials

  • 40x 1 Hose

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equipping the power plant site with the aforementioned materials.

Al-Najaf Power Plant

We have supplied Al-Najaf Power Plant with the following materials

  • PRISMIC R10 EARTH FAULT AERIAL PART No 961503700

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equipping the power plant site with the aforementioned materials.

Bazurkan Power Plant

We have supplied Bazurkan Power Plant with the following materials

  • Rosemount
  • Chanhassen

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equipping the power plant site with the aforementioned materials.

Al-Musayib Power Plant

We have supplied Al-Musayib Power Plant with the following materials

  • AVR PRISMIC A30 Excitation Controller

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equipping the power plant site with the aforementioned materials.

Al-Najaf Gaz Station

We have supplied Al-Najaf Gaz Station with the following materials

  • 3x TSG912 N12 L12

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equipping the power plant site with the aforementioned materials.

Al-Hilla Power Plant

We have supplied Al-Hilla Power Plant with the following materials

  • PMGs

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equipping the power plant site with the aforementioned materials.

Al-Taji Station

We have supplied Al-Taji Station with the following materials

  • 500x Filters

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equipping the power plant site with the aforementioned materials.

Al-Taji Power Plant

We have supplied Al-Taji Power Plant with the following materials

  • 5x Rings

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equipping the power plant site with the aforementioned materials.

Al-Najif Power Plant

We have supplied Al-Taji Power Plant with the following materials

  • 2x UPS

This project was done and delivered within less than the required time limit while sustaining the best bidding price for the project and equipping the power plant site with the aforementioned materials.